Updates on construction progress will be posted here. Check below for information on progress, upcoming works, key milestones and the project timeline below.
Construction Update: Eastern Compound Works
RJ McLeod has commenced work on the Eastern Compound, located off the C72 road between Barrhill and New Luce.
As part of these works, the C72 will be temporarily closed from 15 June to 28 June to allow construction of the site entrance. Details of the temporary road closure have been publicised in Barrhill News.
The works are confined to a relatively short section of the road and access to local properties is not expected to be affected. A signed diversion route will be in place for through traffic during this period.
We thank local residents and road users for their patience and understanding while these works are carried out.
Chirmorie Wind Farm: Project Milestones
April 2026:
Construction commences 27th April. Start of civil engineering works, including construction of a link track between Stranoch and Chirmorie. Initial import of materials to site.
May 2026:
Starting 11th May, activity moves into a more coordinated delivery phase leading to increased traffic.
June 2026:
C72 road works, including minor road upgrades and access preparations from the east side
September 2026:
Transition to increasing use of on-site rock and stone.
Sep 2026 - Nov 2026:
Project moves away from heavy import phase.
Sep 2027 - Oct 2027:
Main civil works largely complete. Includes abnormal load deliveries for Network Rail bridge components and grid transformer.
October 2027:
Installation phase begins. Delivery and erection of wind turbine components, expected duration approximately 8 weeks
Mar 2028 - Apr 2028:
Commissioning and grid testing phase begins.
August 2028:
Expected project completion date