We recognise that traffic and deliveries are among the issues of greatest interest to local communities during construction. This page will therefore provide advance notice, where possible, of planned road works, access arrangements, delivery periods and abnormal load movements associated with the project.

No abnormal loads or wind turbine components will be transported on the C72. Traffic will consist of typical construction vehicles such as HGVs, vans and site welfare units.

Delivery of wind turbine components is expected to begin from September 2027, arriving via the Port of Cairnryan before travelling to the site via the A77, U90w and U84w.

See below for more information on traffic management and deliveries.

April 2026 - May 2026

A77, U90w and U84w

Short-term increase in traffic as construction commences.

Expected traffic: ~10 HGV movements per day on local roads.

C72 Road

Minor road upgrades begin.

May 2026 – September 2026

A77, U90w and U84w

Week commencing 11 May, activity moves into a more coordinated delivery phase.

Expected traffic: ~40-60 HGV movements per day at peak times (spread throughout the day to maintain steady traffic and minimise disruption).

May 2026 – September 2026

C72 Road

Completion of road upgrades.

Expected traffic: ~6-8 movements per day for ~6 weeks.

September 2026 – November 2026

A77, U90w and U84w

As project transitions to using on-site materials, traffic will reduce.

Expected traffic: ~8-10 HGV movements per day.

September 2026 – November 2026

C72 Road

Reduced traffic.

Expected traffic: ~1-2 movements per day.

November 2026 – October 2027

A77, U90w and U84w

Continued reduced traffic.

November 2026 – October 2027

C72 Road

Temporary increase in traffic until March 2027.

Expected traffic: ~6-8 movements per day during increase and ~1-2 post temporary increase.

October 2027 – March 2028

A77, U90w and U84w

Installation phase begins, leading to increase in traffic delivering wind turbine components.

Expected to last: ~8 weeks

October 2027 – March 2028

C72 Road

Continued reduced traffic.

March 2028 – August 2028

A77, U90w and U84w

As project enters grid testing phase there will be significant reductions in traffic, mainly cars and vans until project end date.

C72 Road

Continued reduced traffic.